We optimize our steam blows with quality engineering, and by utilizing the best equipment. Determining pipe sizing and design, pipe routing, steam conditions, noise level, thermal cycling, water quenching, and condensate generation are all factors that with our proper planning will ensure a successful steam blow operation.
When the pipe is fabricated during hot working, a heavy oxide layer forms. This layer is known as the mill scale and must be removed from critical systems before putting them into service.
Over time, enhancements have been made in plant start-up techniques to perform engineered steam blows that remove mill scale. During a steam blow, the piping is blown with sufficient boiler pressure to ensure that enough dynamic pressure will be experienced in the pipe to provide adequate cleaning.
During any plant start-up, there is a possibility that particles left in the pipe from the construction phase could break loose and travel downstream. These particles can damage instrumentation and impede other plant operations. Typically, boiler pressures used in steam blowing provide a dynamic pressure throughout the piping that is at least 20% higher than would be experienced in normal operating conditions (CFR ? 1.2). Any potentially damaging particles will be blown out of the piping prior to plant operation.
The time taken for an object to travel through the system and be ejected cannot be calculated. Instead, a technique of detecting particles in the emerging steam blow is used. This technique checks the emerging steam for particles impacting on a polished metal plate (commonly known as a target).
The steam blow method is similar to the exhaustive air blow technique, but the boiler is fired to generate the pressurized steam used to clean the steam path. Specialized quick-opening valves and a detailed procedure, along with the design of temporary spools, steam quenching devices, silencers, and debris-containing equipment are required to perform this service.
Before putting steam into the system, the control valves, turbine meters, instruments, vacuum ejectors, strainers, etc. should be removed or blinded off. The steam headers should be slowly warmed up, one header at a time, while expansion of the line is observed. Condensate must be drained manually to prevent steam hammering. The headers should now be blown using a low-pressure, high-velocity sweep as explained hereafter. Wherever allowed, only low-pressure steam is to be used if available at temperatures not exceeding 1200C.
When the headers are warm, the drain valves should be opened, and blown vigorously for a few seconds before closing. Each drain valve lateral to the header, exchangers, or service lines should be blown in the same manner, usually not more than one at a time. Condensate lines may be cleaned in the same manner as steam lines. A temporary movable silencer could be used to avoid exceeding noise level limitations during the steam-blowing operation, if necessary.
When the blow-down of the steam system is completed, equipment that was removed prior to the blow-down can be reconnected.
STEAM BLOW SERVICES
Steam blowing is one of the initial cleaning operations before starting any power plant or steam lines. Steam Blowing of MS lines, CRH, HRH, SH, RH, HP & LP bypass pipelines of the turbine are carried out in order to remove welding slag, weld bead deposits, loose foreign materials, iron pieces, rust, etc. from the system, generated during manufacturing, transportation & erection prior to turbine operation. The cleaning is accomplished by subjecting the piping systems to heating, blowing steam, and cooling cycles in sufficient number and duration until clean steam is obtained.
The effect of Steam Blowing depends on the following factors:
Cleaning Force Ratio or CFR of Steam Blowing
STEAM BLOW SERVICES
Steam blowing is a method of cleaning of piping system where the energy and speed of steam are used to remove the impurities from the piping network. The temperature difference during steam blowing is used to remove the mill scale due to the expansion and contraction of the pipe.
The steam-blowing method is similar to the Pressurised Air blowing technique but in this case, a boiler is fired to generate the pressurized steam used for cleaning pipes. Some specialized quick-opening valves with a detailed procedure in parallel with a properly designed temporary network, steam quenching devices, silencers, and debris-containing equipment are used to perform this operation.
When pipe fabrication was under progress during hot working days, an oxide layer is formed on the inside surface of pipes. This layer is known as the mill scale, and this must remove from the system before charging the line with the service.
Cleaning by steam blowing is carried essentially for steam piping networks. Due to the problem of condensation of steam or draining of condensate. During the start-up of any plant, there is a possibility the particles left in the pipe from the construction stage could break and travel downstream. These particles can damage instrumentation and other critical components of the piping network.
In general, Boiler pressure used in steam blowing gives a dynamic pressure throughout the piping that is at least 20% higher than in normal operating conditions. Any potentially damaging particle remaining inside the pipe can blow out the piping system during plant operation.
There are 02 effective ways through which we can perform steam blowing for the internal cleaning of pipes:
In this method of steam blowing, the Piping arrangement for steam blowing is gradually pressurized until a predetermined pressure is reached. Once the required pressure is developed in the steam-blowing system, the Valve connected to it is opened quickly to release steam.
A quick opening of pressurized contained steam in the piping system that needs to clean develops a transonic phase with a high mass flow rate. In order to employ the cyclic blow, temporary piping has to be properly designed, and stress analysis has to be done before starting.
This method is repeated at regular intervals with the same steam pressure and mass flow rate until the cleanliness of the piping system is not determined. Normally, no more than one cycle can be performed daily to ensure adequate cooling of the piping system.
During the pre-commissioning process, it is standard practice to continuously feed low-pressure steam for cleaning most steam piping systems. This method of steam blowing requires steam generators that continuously generate and fire steam.
In this case, the velocity developed by the steam generator is higher than the velocity of steam during normal plant operation. To control the pre-determined and required velocity of steam an orifice plate is installed at the inlet of the piping system, The steam with low pressure continuously blows until a satisfactory level of cleaning is achieved.
A typical most efficient conditional parameter for continuous steam blowing is:
After preparation of all points in the pre-cleaning procedure for steam blowing. The actual process of steam blowing starts with the permission of deciding authority in the control room. Steam bowing procedures to be followed are: